VERO BEACH – Drainage work will continue on 20th Avenue Monday after it began Tuesday, Sept. 14. SPS Contracting Inc. is installing drainage pipes across the north and southbound lanes at 19th Avenue.
The construction will last through Wednesday and will include closing down no more than one lane of 20th Avenue at a time. A minimum of one lane of southbound traffic will remain open at all times on 20th Avenue.
Flagmen, barrels, signs, and all necessary traffic control will be provided during this construction.
A minimum of one lane of northbound and one lane of southbound traffic will remain open at all times on 20th Avenue.
Additionally, on Monday, Sept. 20, 19th Street west of 20th Avenue will be closed between 21st Avenue and 20th Avenue.
Traffic will be detoured either north or south on 21st Avenue. Nineteenth Street will be accessible to local traffic only from 21st Avenue to 20th Avenue for access to residences.